116 — Phase 1 Build Preflight After Approval — NOT_RUN (Hard Gate B not reached, 2026-06-01)
2 min read Revision 1
one-roof-governanceimplementation-indexphase1build-preflighthard-gate-bnot-run2026-06-01
116 — Phase 1 Build Preflight After Approval (Hard Gate B)
Status: NOT_RUN. Hard Gate B (build preflight) is only reached after Phase A passes. Phase A is BLOCKED (docs 114/115): M-1 = 0, no approval/intake record created. Therefore Hard Gate B was not entered and no build preflight for a COMMIT was performed.
116.1 Gate B checklist — state at this run
| Gate B item (mission §4) | Required | Actual | Pass? |
|---|---|---|---|
| 1. Re-run doc 96 preflight | green | baseline matches doc 96 exactly (doc 114 §114.8) | n/a — not a build trigger |
| 2. M-1 green for the specific step | green | RED (os_proposal_approvals = 0) | FAIL → STOP |
| 3. Council C-1/C-2/C-7 satisfied for current step | recorded | not present | FAIL |
| 4. Backup/rollback artifacts staged | staged | not staged (no build) | n/a |
| 5. Target objects state | absent/expected | all 6 SB targets ABSENT (expected) | ok |
| 6. Stop conditions clear | clear | stop condition M-1=0 is ACTIVE |
FAIL → STOP |
116.2 Verdict
Gate B item 2 (M-1) and item 6 (active stop condition) fail. STOP. No build preflight-to-COMMIT performed. The read-only baseline is recorded in doc 114 §114.8 as evidence the substrate is untouched.