dot-iu-cutter v0.1 — P0 Blocker Closure Dashboard

12 min read Revision 1
dot-iu-cutterblocker-closuredashboardp0critical-pathno-executionno-ddlrev5d

dot-iu-cutter v0.1 — P0 Blocker Closure Dashboard

Date: 2026-05-15 Status: BLOCKER CLOSURE PROGRAM — Dashboard Scope: PLANNING DOCUMENTATION ONLY. No closure performed. Master: blocker-closure/dot-iu-cutter-v0.1-p0-blocker-closure-master-plan-2026-05-15.md


1. Purpose

Provide a single-table view of all 9 hard blockers (HB-01..HB-09) and 4 conditions-to-execute (CTE-01..CTE-04). For each:

  • status (open / ready_to_close / blocked / deferred)
  • owner
  • upstream dependency
  • closure artefact required
  • whether it blocks the first DDL
  • next action
  • whether it sits on the critical path

Status definitions:

  • open — work not yet started; ready to start when dependencies allow
  • ready_to_close — all dependencies satisfied; closure work can begin now
  • blocked — dependency on another blocker not yet closed
  • deferred — does not need to close for v0.1 P0 (e.g., G-1, G-3 seats; FUTURE items)

Today's snapshot has no closures performed, so all entries are either ready_to_close (independent items) or blocked (items waiting on upstream).

2. Source Inputs

  • final-readiness/dot-iu-cutter-v0.1-p0-final-readiness-blocker-register-2026-05-15.md
  • blocker-closure/dot-iu-cutter-v0.1-p0-blocker-closure-master-plan-2026-05-15.md
  • blocker-closure/dot-iu-cutter-v0.1-p0-workstream-a-governance-seats-signoffs-2026-05-15.md
  • blocker-closure/dot-iu-cutter-v0.1-p0-workstream-b-vocabulary-schema-canonicalization-2026-05-15.md
  • blocker-closure/dot-iu-cutter-v0.1-p0-workstream-c-infrastructure-preflight-dryrun-2026-05-15.md

3. Hard Blockers Dashboard

ID Title Status Owner Upstream dependency Closure artefact Blocks first DDL Next action Critical path
HB-01 X-1 schema placement sign-off (cutter_governance; P0-1 stays TAC) ready_to_close Đ44 + Đ33/Đ43 none ratification file binding schema class name + membership + permission/role mapping yes open Đ44 + Đ33/Đ43 session; produce ratification file parallel to critical
HB-02 X-4 Đ24 enum-set ratification + lookup-table population ready_to_close Đ24 + Đ44 none (a) Đ24 ratification file; (b) operational lookup population artefact yes open Đ24 session for ratification; schedule operational lookup population parallel to critical
HB-03 X-6 dot_pair_signature shape sign-off (revocation lifecycle + exactly-one cross-reference) blocked G-4 + Đ44 HB-06 G-4 named ratification file binding polished shape + revocation lifecycle + exactly-one rule yes (Step 5) wait for HB-06 G-4; then convene G-4 + Đ44 sign-off on critical path
HB-04 X-7 canonicalization rule prose ratification + identifier ready_to_close Đ24 + Đ44 none ratification file binding identifier (canon-md-v0.1.0 or final) + full prose yes (Step 6) open Đ24 + Đ44 session for prose ratification on parallel critical chain via CTE-03 → HB-05
HB-05 X-8 rollback test plan dry-run + Đ32 + G-4 sign-off blocked Đ32 (HIGH-risk) + G-4 HB-06, HB-03, HB-07, HB-09, HB-04, CTE-02, CTE-03, CTE-04 closure file: 26-scenario outcomes (100% pass) + Đ32 + G-4 sign-off yes wait for ALL upstream; LAST closure on critical path; terminal
HB-06 Operational seats G-2, G-4, G-5 named (Đ37) ready_to_close Đ37 none Đ37 seat assignment records for G-2, G-4, G-5 yes (G-2, G-4, G-5 subset) open Đ37 operational session; name three seats on critical path; start here
HB-07 DOT-pair registration (executor + verifier) + tool_revision drift rule binding blocked G-4 HB-06 G-4 named; HB-03 recommended DOT registry records for dot-iu-cutter + dot-iu-cutter-verify; drift rule binding yes (Step 5+) wait for HB-06 G-4 + HB-03; then G-4 records registry entries on critical path
HB-08 Directus PG backup + restore test blocked G-4 + operational DBA HB-06 G-4 named backup file + restore-test artefact + sign-off yes wait for HB-06 G-4; then DBA performs backup + restore test parallel to critical
HB-09 Schema + row-count snapshots + dry-run environment blocked Operational DBA + G-2 HB-06 G-2 named (for backlog artefact) schema snapshot + row-count snapshot + dry-run environment yes wait for HB-06 G-2; then DBA + G-2 produce snapshots; provision environment parallel to critical
hard_blockers_total: 9
ready_to_close_today: 4 (HB-01, HB-02, HB-04, HB-06)
blocked_today: 5 (HB-03, HB-05, HB-07, HB-08, HB-09)
deferred_today: 0
closed_today: 0

4. Conditions-to-Execute Dashboard

ID Title Status Owner Upstream dependency Closure artefact Blocks first DDL Next action Critical path
CTE-01 Failure-stop rule enforced at execution time planning_closed; execution_open G-4 + operational DBA none (planning-level documented per preflight plan §8) execution-time tool/runbook enforces failure-stop no for planning; yes at execution-time for production safety nothing in this phase; execution-phase runbook task not on critical path (execution-time)
CTE-02 Signal routing wired (dot_pair_drift / signature_failure → G-2) blocked G-2 + G-4 HB-06 G-2 + HB-06 G-4 + HB-07 configured G-2 backlog channel + emission binding + capability proof effective yes (via HB-05) wait for HB-06 G-2/G-4 + HB-07; then wire channel on critical path (via HB-05)
CTE-03 Canonicalization library scaffolding (v0.1) blocked Engineering + G-3 oversight HB-04 scaffold + determinism test logs effective yes (via HB-05) wait for HB-04; then engineering scaffolds library on critical path (via HB-05)
CTE-04 Signing scheme v0.1 (hash-based pseudo-signature) implementation blocked G-4 + Engineering HB-06 G-4 + HB-03 implementation + capability proofs + G-4 sign-off effective yes (via HB-05) wait for HB-06 G-4 + HB-03; then engineering implements + G-4 signs off on critical path
cte_total: 4
ready_to_close_today: 0
blocked_today: 3 (CTE-02, CTE-03, CTE-04)
planning_closed_today: 1 (CTE-01; execution-phase concern carries forward)
closed_today_completely: 0

5. Post-Execution Follow-ups Dashboard (do NOT block first DDL)

ID Title Status Owner Blocks first DDL
PEF-01 canonical_address backfill deferred G-2 + DBA no
PEF-02 canonical_address NOT NULL enable post-backfill deferred DBA + G-2 no
PEF-03 PG-constraint dual-signature enforcement deferred G-4 + Đ32 no
PEF-04 Cryptographic signing scheme upgrade deferred G-3 + G-4 + Đ32 no
PEF-05 Per-source_kind canonicalization extensions deferred Đ24 + G-3 no
PEF-06 axis-2 elevation review deferred G-3 + Đ32 no
PEF-07 Markdown mirror generator deferred G-2 + Đ37 no
PEF-08 PG jsonb_check rollout deferred Đ44 + Đ24 + engineering no
PEF-09 DOT-pair separate execution context implementation deferred G-3 + G-4 + Đ32 no

All PEF items are deferred because they are FUTURE / post-execution and do NOT block first DDL. They are tracked here for completeness.


6. Critical Path Visualization

The critical path is the longest chain of dependencies that must be sequentially closed before the execution gate can become conditionally openable:

[HB-06 G-4 named]
        │
        ▼
[HB-03 X-6 polish signed]
        │
        ▼
[HB-07 DOT-pair registered]
        │
        ▼
[CTE-04 signing scheme v0.1 implemented]
        │
        └──────┐
               │
[HB-04 Đ24 prose] ──▶ [CTE-03 canon library scaffolded]
                                                 │
                                                 │
[HB-06 G-2 named] ─▶ [CTE-02 signal channel wired]
                                                 │
                                                 │
[HB-09 dry-run env provisioned] ────────────────▶ │
                                                 │
                                                 ▼
                                          [HB-05 26-scenario
                                           dry-run + Đ32+G-4 sign-off]
                                                 │
                                                 ▼
                                          [Re-run Final
                                           Readiness Review]
                                                 │
                                                 ▼
                                          [Explicit user prompt
                                           authorizing execution]
                                                 │
                                                 ▼
                                          [Execution phase
                                           (first DDL allowed)]
critical_path_summary:
  primary_chain: HB-06 G-4 → HB-03 → HB-07 → CTE-04 → HB-05
  parallel_required_chain_1: HB-04 → CTE-03 → HB-05
  parallel_required_chain_2: HB-06 G-2 → CTE-02 → HB-05
  parallel_required_chain_3: HB-09 → HB-05
  terminal_node: HB-05 (rollback test plan dry-run + sign-off)
  followed_by: re-run Final Readiness Review → explicit user prompt → execution phase

parallel_independent_to_critical_path:
  - HB-01 (schema placement sign-off) — independent of seat naming; needed for first DDL but NOT for HB-05 dry-run if dry-run uses isolated environment
  - HB-02 (Đ24 enum ratification + lookup population) — independent of seat naming; needed for first DDL
  - HB-08 (backup + restore test) — independent of HB-05 dry-run; needed for production execution

minimum_calendar_chain_to_close: HB-06 G-4 + HB-03 + HB-07 + CTE-04 + HB-05 (each requires its own session; some can overlap if parallel chains are scheduled correctly)

7. Next Action Per Blocker (Compact)

next_actions_today:
  HB-01: open Đ44 + Đ33/Đ43 session
  HB-02: open Đ24 session for enum-set ratification; schedule operational lookup population
  HB-04: open Đ24 + Đ44 session for canonicalization prose ratification
  HB-06: open Đ37 operational session to name G-2, G-4, G-5 (recommended first action)
  HB-03: wait for HB-06 G-4
  HB-05: wait for all upstream
  HB-07: wait for HB-06 G-4 + HB-03
  HB-08: wait for HB-06 G-4
  HB-09: wait for HB-06 G-2
  CTE-01: planning-level closed; execution-phase concern
  CTE-02: wait for HB-06 G-2/G-4 + HB-07
  CTE-03: wait for HB-04
  CTE-04: wait for HB-06 G-4 + HB-03

8. Status Counts (Snapshot)

status_snapshot_2026_05_15:
  hard_blockers:
    open_total: 9
    ready_to_close: 4 (HB-01, HB-02, HB-04, HB-06)
    blocked: 5 (HB-03, HB-05, HB-07, HB-08, HB-09)
    deferred: 0
    closed: 0
  cte:
    open_total: 4
    ready_to_close: 0
    blocked: 3 (CTE-02, CTE-03, CTE-04)
    planning_closed: 1 (CTE-01)
    closed_completely: 0
  pef:
    total: 9; all deferred (do not block first DDL)
  closures_performed_in_this_planning_phase: 0
  execution_authorized: false

9. Explicit Confirmation

no_closure_performed: true
no_seat_named: true
no_role_created: true
no_dot_pair_registered: true
no_signing_scheme_implemented: true
no_signal_channel_wired: true
no_library_scaffolded: true
no_backup_taken: true
no_snapshot_taken: true
no_environment_provisioned: true
no_dry_run_executed: true
no_ratification_file_issued_in_this_dashboard: true
no_ddl_written: true
no_sql_written: true
no_migration_executed: true
no_pg_mutation: true
no_qdrant_mutation: true
no_directus_mutation: true
no_data_writes: true
no_execution_authorized: true
no_phase_prior_file_modified: true
output_form: blocker_closure_dashboard_only